Vacancy Notice – 14.6.23
-
Vacancy Notice
-
Bridge Works – Phase 1 Repairs
Phase 1 repairs: grouting of void and surfacing.
Works are planned to start Monday 17th April late afternoon (slack water), while works are being carried out the bridge will be under a full closure with no temporary footway allowing pedestrians to cross. Please see a program of works below which may be subject to change:
- Afternoon of Monday 17th April 1500hrs till late evening, waterway and temporary footway will be under a full closure allowing for a safe working zone for divers and operatives on bridge.
- Tuesday curing time for grout (temporary footway over the bridge open for pedestrians)
- Wednesday and Thursday filling/compacting fill material in void (temporary footway over the bridge closed during working hours only).
- Friday contingency for any unexpected issues that may arise (temporary footway over the bridge open unless additional works required)
- Saturday/Sunday (temporary footway over the bridge will remain open to pedestrians)
- Monday 24th to Wednesday 26thth April full closure 24hrs a day for surfacing/lining works.
- Late Wednesday afternoon the road will be open to all traffic within signed weight restrictions
-
Planned maintenance on the flood defence embankments